Turf Maintenance

Levee turf maintenance progress across the system

The maintenance plan

Routine mowing across 3,633 acres of levee turf

SLFPA-E maintains 3,633 acres of levee turf across 14 zones in three levee districts. Mowing targets vary by zone based on size, location, and operating conditions. This dashboard shows monthly progress against those targets using a simple Green / Amber / Red status, as defined in the “How to read the zone cards” section below.

System overview

October 2026 system status
6 of 7 reporting zones on pace this month
7 of 14 zones awaiting weekly update
Watch
3,633
total acres maintained
14
zones across 3 districts
3
levee districts (OLD, EJLD, LBBLD)
104.79
total miles maintained

Mowing data reflects the October 2026 reporting period and is updated weekly as the maintenance team submits progress.

Operational Note — September 2026

Levee turf maintenance is slightly behind due to recent rain but catching up as weather conditions improve; no readiness impacts reported.

The dashboard will continue to show actual progress against monthly mowing targets. Status colors are not adjusted for weather impacts, but operational notes will be provided when conditions materially affect monthly progress.

District:

Zones across the system

Mowing-area polygons colored by zone. Click any polygon for its name, zone, and acreage.

Loading map...

Showing all three districts: Orleans (144 polygons across 6 zones, ~1,620 acres), East Jefferson (63 polygons across 4 zones, ~660 acres), and Lake Borgne Basin (84 polygons across 4 zones, ~1,353 acres).

How to read the zone cards

Each card shows how much of the zone's monthly mowing target has been completed in October 2026. The bar fills with cumulative acres mowed against the monthly target (zone acres × cycles per month). The dark tick marks where Cycle 1 should land for zones running more than once per month.

The mowing status reflects progress against the monthly mowing target for each zone. It is an operational production indicator and does not, by itself, indicate a deficiency in the flood protection system. Weather, saturated ground conditions, site access, safety considerations, equipment availability, and other operating conditions may affect daily mowing production. When those conditions materially affect monthly progress, SLFPA-E may provide an operational note explaining the cause and recovery actions.

  • On pace — at or above 90% of monthly target
  • At risk — 80 to 89% of monthly target
  • Behind — under 80% of monthly target

Use the Cycle pace % toggle above the cards to switch each bar between acres completed and the percentage of the monthly cutting goal completed — the same figure that sets each zone's status.

Show:

Orleans Levee District Zones

6 color-coded zones. October 2026.

Zone

New Orleans East

650 ac · 1.5×/mo · 975 ac target

Reaches

  • LPV-108141 ac
  • LPV-109289 ac
  • LPV-111220 ac
Monthly progressAwaiting weekly update

Monthly target 975 ac

Zone

Southside MRGO & Citrus Back

307 ac · 2×/mo · 614 ac target

Reaches

  • Southside MRGO (LPV-142/LPV-143)185 ac
  • Citrus Back Levee — LPV-115 (Paris Rd. Bridge to Jourdan Rd)122 ac
Monthly progressAwaiting weekly update

Monthly target 614 ac

Zone

Lakefront & Outfall Canals

300 ac · 2×/mo · 600 ac target

Reaches

  • Lakefront95 ac
  • Outfall Canals (17th Street, Orleans, Bayou St. John, London)123 ac
  • IHNC West57 ac
  • IHNC East (E-13 to N-01)25 ac
October 2026 progressOn pace

200 of 600 ac completed this month

Zone

Citrus Lakefront & Eastern Interior

253 ac · 1.5×/mo · 380 ac target

Reaches

  • Citrus Lakefront57 ac
  • Paris Rd12 ac
  • Maxent41 ac
  • Michoud Canal Floodwall75 ac
  • NASA52 ac
  • Entergy16 ac
Monthly progressAwaiting weekly update

Monthly target 380 ac

Zone

Upper Protection

53 ac · 2×/mo · 106 ac target

Reaches

  • Upper Protection (Earhart Blvd to the MRL)8 ac
  • MRL (Jefferson Parish line to EB-00)45 ac
Monthly progressAwaiting weekly update

Monthly target 106 ac

Zone

Florida Ave

57 ac · 2×/mo · 114 ac target

Reaches

  • Florida Ave10 ac
  • IHNC East (E-01 to MRL)21 ac
  • MRL (IHNC East to St. Bernard Parish line)26 ac
Monthly progressAwaiting weekly update

Monthly target 114 ac

East Jefferson Levee District Zones

4 color-coded zones. October 2026.

Zone

EJ Lakefront Reach 1-5

360 ac · 2×/mo · 720 ac target

Reaches

  • St. Charles/Jeff Parish line to 17th St. Canal on EJ side360 ac
October 2026 progressOn pace

360 of 720 ac completed this month

Zone

EJ MRL

205 ac · 2×/mo · 410 ac target

Reaches

  • Monticello to Alliance202 ac
  • St. Charles/Jeff Parish line3 ac
October 2026 progressOn pace

206 of 410 ac completed this month

Zone

EJ West Return

85 ac · 2×/mo · 170 ac target

Reaches

  • Airline Hwy & Lesan Dr to St. Charles/Jeff Parish line (Reach 1)85 ac
October 2026 progressOn pace

64 of 170 ac completed this month

Zone

EJ East Return

10 ac · 2×/mo · 20 ac target

Reaches

  • Along 17th St. Canal to Pinks St10 ac
Monthly progressAwaiting weekly update

Monthly target 20 ac

Lake Borgne Basin Levee District Zones

4 color-coded zones. October 2026.

Zone

LPV-144 through LPV-149

592 ac · 1×/mo · 592 ac target

Reaches

  • Bayou Dupre Structure (St. Bernard side) to HWY 39 at MRL592 ac
October 2026 progressBehind

59 of 592 ac completed this month

Zone

Non-Federal Back Levee/NFL

316 ac · 1×/mo · 316 ac target

Reaches

  • 40 Arpent Levee — Orleans Parish line to HWY 46 Reggio in lower St. Bernard316 ac
October 2026 progressOn pace

316 of 316 ac completed this month

Zone

LPV-145

278 ac · 1×/mo · 278 ac target

Reaches

  • "The Island" (Bayou Bienvenue Structure to Bayou Dupre Structure)278 ac
Monthly progressAwaiting weekly update

Monthly target 278 ac

Zone

MRL

167 ac · 1×/mo · 167 ac target

Reaches

  • Mississippi River Levee at HWY 39 to Arabi (Orleans Parish line)167 ac
October 2026 progressOn pace

84 of 167 ac completed this month