Engineering
Permits, inspections, and engineering contracts
Data source: May 2026 SITREP
Federal & State Inspections
CPRA Quarterly Inspection
State-mandated quarterly visual inspection of the levee system, with findings reported to the Coastal Protection and Restoration Authority.
USACE Semi-Annual Inspection
Federal inspection of HSDRRS levees, floodwalls, PCCPs, and complex structures. 100% = on pace for this point in the half-year cycle.
Current Capital Projects
Major capital projects currently under contract, in construction, or in active bidding.
Foreshore Erosion Repair
In ProgressUSACE has determined path forward; target award June 2026
Source: Apr 2026 SITREP
West Return Wall Splash Pad
In ProgressConstruction ongoing, approximately 95% complete
Source: Apr 2026 SITREP
LPV Access Bridge
AwardedContract executed; preconstruction meeting scheduled
Source: Apr 2026 SITREP
Orpheum Slope Paving
AwardedAwarded during February Board Meeting; contract execution ongoing
Source: Apr 2026 SITREP
Lakeside Drive (Elysian Fields to Franklin Ave)
CompleteSafety improvement project completed on schedule
Source: Apr 2026 SITREP
Franklin Ave Vault 4
In BiddingFinal bid documents under review; advertisement to follow
Source: Apr 2026 SITREP
Permits
Source: May 2026 SITREP
Source: FPA Engineering Department
Last 4 Quarters
Source: FPA Engineering Department
Permit Processing Pipeline
Permit flow (last 4 quarters)
Source: FPA Engineering Department
Avg 69 days submittal to LNO (Letter of No Objection), 38 days LNO to approval (last 4 quarters)
Permits Issued
Monthly Permits Trend
| Month | Permits Issued | Source |
|---|---|---|
| September 2025 | 25 | Oct 2025 SITREP |
| October 2025 | 50 | Nov 2025 SITREP |
| November 2025 | 46 | Dec 2025 SITREP |
| December 2025 | 10 | Jan 2026 SITREP |
| January 2026 | 42 | Feb 2026 SITREP |
| February 2026 | 25 | Mar 2026 SITREP |
| March 2026 | 27 | Apr 2026 SITREP |
| April 2026 | 27 | May 2026 SITREP |
Source: SITREPs
Routine Maintenance Activities
Current Maintenance Work
- Completed 24 earthen levee repairs from in-house work orders
- Completed 27 floodwall surface spall repairs on sections, joints, and slope pavement
- Hurricane gate annual inspections 45% complete
- Q1 2026 valve inspections and exercises complete
- Deslonde Street levee access gate installed
- New wiring installed at police station for camera monitors; chiller 3 water meter installed with weekly usage tracking
- Assisting CPRA with 500-tree planting for ongoing mitigation project
Source: Apr 2026 SITREP