Engineering
Permits, inspections, and engineering contracts
Data source: August 2026 SITREP
Federal & State Inspections
CPRA Quarterly Inspection
State-mandated quarterly visual inspection of the levee system, with findings reported to the Coastal Protection and Restoration Authority.
USACE Semi-Annual Inspection
Federal inspection of HSDRRS levees, floodwalls, PCCPs, and complex structures. 100% = on pace for this point in the half-year cycle.
Current Capital Projects
Major capital projects currently under contract, in construction, or in active bidding.
Foreshore Erosion Repair
In BiddingBoard approved CEA with Pontchartrain Levee District for borrow site Right of Entry; USACE schedule to advertise in July with Bid Opening August 21, 2026; mitigation measures being scheduled at two eroded locations.
Source: August 2026 SITREP
West Return Wall Splash Pad
In ProgressConstruction is substantially complete. Project in closeout phase.
Source: August 2026 SITREP
LPV Access Bridge
In ProgressConstruction has begun. Contractor is mobilizing. RFI / shop drawings submittals underway.
Source: August 2026 SITREP
Orpheum Slope Paving
In ProgressConstruction has begun. Staged concrete pours are underway.
Source: August 2026 SITREP
Franklin Ave. Vault 4 – Final
In ProgressConstruction ongoing.
Source: August 2026 SITREP
London Avenue Canal Erosion Mitigation (Phase 1)
In BiddingCurrently advertising with a bid opening of August 11, 2026. Construction award and CEA with City of New Orleans to be presented to Board for approval during August meeting.
Source: August 2026 SITREP
40 Arpent Sheet Pile Rehabilitation (Phase 2)
In DesignSurvey has been completed and design underway.
Source: August 2026 SITREP
Franklin Herbicide Vehicle Containment
Pre-AwardReadvertisement yielded 3 quotes. Project initiation underway.
Source: August 2026 SITREP
Lakeshore Drive Flooding Warning Signs
In DesignIDIQ holder engaged for design of locations; currently exploring exact locations and coordinating design for installation with IDIQ holder.
Source: August 2026 SITREP
Tropical Storm Arthur – Franklin Facility Damage
AwardedEngineering accepted bids for removal of damaged areas. Demolition work to begin August 10, 2026, with a contract duration of 45 days.
Source: August 2026 SITREP
Permits
Life of a permitView permit data
Source: FPA Engineering Department
Monthly Permits Issued
| Month | Permits Issued | Source |
|---|---|---|
| July 2026 | 33 | August 2026 SITREP |
| May 2026 | 19 | June 2026 SITREP |
| April 2026 | 27 | May 2026 SITREP |
| March 2026 | 27 | Apr 2026 SITREP |
| February 2026 | 25 | Mar 2026 SITREP |
| January 2026 | 42 | Feb 2026 SITREP |
| December 2025 | 10 | Jan 2026 SITREP |
| November 2025 | 46 | Dec 2025 SITREP |
| October 2025 | 50 | Nov 2025 SITREP |
| September 2025 | 25 | Oct 2025 SITREP |
Source: SITREPs
Routine Maintenance Activities
Current Maintenance Work
- Completed 24 earthen levee repairs from in-house work orders
- Completed 27 floodwall surface spall repairs on sections, joints, and slope pavement
- Hurricane gate annual inspections 45% complete
- Q1 2026 valve inspections and exercises complete
- Deslonde Street levee access gate installed
- New wiring installed at police station for camera monitors; chiller 3 water meter installed with weekly usage tracking
- Assisting CPRA with 500-tree planting for ongoing mitigation project
Source: Apr 2026 SITREP