Engineering
Permits, inspections, and engineering contracts
Data source: October 2026 SITREP
Federal & State Inspections
CPRA Quarterly Inspection
State-mandated quarterly visual inspection of the levee system, with findings reported to the Coastal Protection and Restoration Authority.
USACE Semi-Annual Inspection
Federal inspection of HSDRRS levees, floodwalls, PCCPs, and complex structures. 100% = on pace for this point in the half-year cycle.
Current Capital Projects
Major capital projects currently under contract, in construction, or in active bidding.
Foreshore Erosion Repair
In BiddingCurrently advertised with a Bid Opening of October 19, 2026.
Source: October 2026 SITREP
LPV Access Bridge
In ProgressConstruction has begun. Contractor has mobilized and is progressing.
Source: October 2026 SITREP
Orpheum Slope Paving
In ProgressConstruction has begun and is progressing per the schedule.
Source: October 2026 SITREP
Franklin Ave. Vault 4 – Final
In ProgressConstruction ongoing and on schedule.
Source: October 2026 SITREP
London Avenue Canal Erosion Mitigation (Phase 1)
AwardedFull NTP scheduled to be issued on 10/12/26 with an expected start of activities within the canal around 11/1/26.
Source: October 2026 SITREP
40 Arpent Sheet Pile Rehabilitation (Phase 2)
In Design60% design submittal currently under review by Engineering.
Source: October 2026 SITREP
Franklin Herbicide Vehicle Containment
In ProgressConstruction has begun and is 95% complete.
Source: October 2026 SITREP
Lakeshore Drive Flood Warning Signs
In Design60% Design submitted. Review comments have been forwarded to designer. 90% design underway.
Source: October 2026 SITREP
Franklin Facility Access Improvements
In Design60% Design submittal under review by Engineering.
Source: October 2026 SITREP
Tropical Storm Arthur – Franklin Facility Damage
In DesignDemolition work has been completed. Secondary structural inspection by adjuster to take place. Engineering continues to coordinate with Maintenance, Finance and Insurance Adjusters. Final repair design scope being determined.
Source: October 2026 SITREP
Permits
Life of a permitView permit data
Source: FPA Engineering Department
Monthly Permits Issued
Months without a published SITREP count are left blank.
| Month | Permits Issued | Source |
|---|---|---|
| September 2026 | 32 | October 2026 SITREP |
| August 2026 | 29 | October 2026 SITREP |
| July 2026 | 33 | August 2026 SITREP |
| May 2026 | 19 | June 2026 SITREP |
| April 2026 | 27 | May 2026 SITREP |
| March 2026 | 27 | Apr 2026 SITREP |
| February 2026 | 25 | Mar 2026 SITREP |
| January 2026 | 42 | Feb 2026 SITREP |
| December 2025 | 10 | Jan 2026 SITREP |
| November 2025 | 46 | Dec 2025 SITREP |
| October 2025 | 50 | Nov 2025 SITREP |
| September 2025 | 25 | Oct 2025 SITREP |
Source: SITREPs
Routine Maintenance Activities
Current Maintenance Work
- Completed 24 earthen levee repairs from in-house work orders
- Completed 27 floodwall surface spall repairs on sections, joints, and slope pavement
- Hurricane gate annual inspections 45% complete
- Q1 2026 valve inspections and exercises complete
- Deslonde Street levee access gate installed
- New wiring installed at police station for camera monitors; chiller 3 water meter installed with weekly usage tracking
- Assisting CPRA with 500-tree planting for ongoing mitigation project
Source: Apr 2026 SITREP